PHIL Supervised Installation for Rear Eject Bodies is required in an effort to ensure proper commissioning of the equipment. Two options for Rear Eject Body Installation are available:
1. FIELD INSTALLATION WITH SUPERVISORY ASSISTANCE:
PHIL will provide a working supervisor to assist in commissioning the PHIL Rear Eject Body for a nominal charge. This installation supervisory assistance is available with a minimum of sixteen (16) days notice. Installation time may vary depending upon field conditions.
PHIL Rear Eject Body Field Installation Requirements:
- PHIL Rear Eject Body shipped assembled, along with miscellaneous small parts.
- Mounting of body to truck chassis.
- Mounting of hydraulic manifold to truck chassis.
- Connect plumbing from truck hydraulic system to hydraulic manifold and rear eject body cylinder.
- Test, validate, and adjust PHIL Rear Eject Body as needed for proper operation.
Customer Supplied:
- Location for hydraulic manifold return to hydraulic tank line to plumb into hydraulic tank.
- Hydraulic hoses and fittings from truck hydraulic sources to hydraulic manifold/valve.
- Hydraulic hoses from hydraulic manifold to rear eject body cylinder.
- Two (2) service technicians, with welding experience.
- Welding equipment as necessary.
- Lifting equipment.
- Miscellaneous hand tools, pry bars, etc.
- O.E.M. body pads, pivot pins, and miscellaneous accessory hardware as needed.
2. BODY TO CHASSIS INSTALLATION AT PHIL FACTORY:
Factory installation of the PHIL Rear Eject Body to truck chassis is the easiest form of installation. Installed price includes miscellaneous hoses for a nominal charge per PHIL Rear Eject Body. Pivot pins and body pads are the responsibility of the purchaser.
PHIL Rear Eject Factory Installation Procedures:
- Purchaser supplies truck/chassis to PHIL factory.
- Mounting of body to truck chassis.
- Mounting of hydraulic manifold to truck chassis.
- Supply and connect plumbing of rear eject body to hydraulic manifold and chassis hydraulic system.
- Test, validate, and adjust PHIL Rear Eject Body as needed for proper operation.
- Chassis with Rear Eject Body ships to customer's preferred location (F.O.B. Peoria, IL).
- PHIL installer visits end user location for commissioning of unit and installation of O.E.M. body pads and pivot pins.
Approximate Installation Time:
The approximate time required to install a PHIL Rear Eject Body in the field would be as follows, depending on product and upon the extend field conditions:
Standard Capacity Articulated Rear Eject: 20 – 35 man hours +/-
HiVol® Refuse Rear Eject: 35 – 45 man hours +/-
HiVol Scrap Steel Rear Eject: 35 – 45 man hours +/-
HiVol Underground Rear Eject: 20 – 35 man hours +/-